Writers : Vahedi,Sarah;Nasseh, Sepideh;Ghafoori,Mohammad; Lashkaripoor, Gholam Reza
Refference : The first international applied geological congress; Department of geology Islamic azad university- Mashhad
Publishing Year : 2010
Abstract :
The light train project of Mashhad city has been started in 1381 to help the transportation system in the city. The third line of this project has approximately 19 Km length, from northwest to southeast. Low ground water table is helpful in this project because this line will be done as a tunnel. Engineering properties of soil is so important in developmental and constructive plans. This paper deals with the geotechnical and geological engineering characteristics of the third line of Mashhad light train. Finally, the soil profile is presented according to correlation between boreholes information, sampling and geotechnical data.
Subject List :
geotechnic